Subcontract packages

Work a subcontractor does under your job

  • A main project
Project coordinator

New package

Project coordinator

New package

1Step 1 of 2

  1. Projects → New project, Project kind Subcontract package.
  2. Choose the Parent project, enter the Subcontractor name, the Awarded scope and the promised date.
  3. Create package.

Open in Stone ↗Full image ↗

Project coordinator · Subcontract packages01

Activate, then complete

Project coordinator

Activate, then complete

2Step 2 of 2

  1. On the package, press Activate package when the work starts and confirm. The accountant can then record its costs.
  2. When the scope is done, press Complete package, give the reason and confirm.

Open in Stone ↗Full image ↗

Check

The package is complete, with its subcontractor, scope and costs on record

Project coordinator · Subcontract packages02